Construction of new Zagreb airport terminal scheduled for Sept
![Zagreb, March 20 2013 - Sinisa Hajdas Doncic Minister attended the presentation of the project of construction of passenger terminal ZL Zagreb with associates from the Ministry and representatives of the concessionaire company Zaić, Christophe Petite and Arnaud Sabatier, project director of the Aeroport de Paris](https://mmpi.gov.hr/UserDocsImages/arhiva/2%20minSHDoncic-ZAIC%2020-3_13.jpg)
The new terminal will consist of 65,000 square metres and will be able to handle five million passengers a year. The project envisages a new airport ramp and a car park.
The financial construction is almost complete, negotiations are drawing to a close, while loan contracts are to be signed and a building permit application filed in April, Christophe Petit explained on behalf of the concessionaire company Bouygues Batiment International.
Once the contracts are signed, ZAIC should take over ZLZ, Petit said, and at the same time make a concession payment of the first EUR 2 million. An equal payment will be made a year later, and for the duration of the concession a percentage of
![Zagreb, March 20 2013 - Minister Sinisa Hajdas Doncic said that the airport investment was valued at EUR 236 million and the end result would be to increase the number of passengers coming to Zagreb and that the airport would become one of the regional junctures for air traffic](https://mmpi.gov.hr/UserDocsImages/arhiva/1%20minSHDoncic-ZAIC%2020-3_13.jpg)
Petit explained that loans had so far been secured from the Unicredit Grupa/Zagrebacka Banka and Erste Banka for EUR 65 million each and from the European Investment Bank (EIB) for EUR 120 million.
Aeroport de Paris project director Arnaud Sabatier said that the concessionaire group consisted of TAV and Bouygues Batiment International, with a 65% share, the IFC corporation which is part of the World Bank with a 20% share, Croatia's insurance company Croatia Osiguranje with a 10% share and the Viadukt construction company with a 5% share.
ZAIC has already invested EUR 4 million in the ZLZ project and its founders, Bouygues Batiment International and Aeroports de Paris Management, deposited to the Croatian government EUR 75.8 million in guarantees and a EUR 20 million execution guarantee, said Sabatier.
![Zagreb, March 20 2013 - The presentation was held at the Ministry of Transport and Infrastructure and was accompanied by a large number of journalists and media representatives](https://mmpi.gov.hr/UserDocsImages/arhiva/3%20minSHDoncic-ZAIC%2020-3_13.jpg)
The French company underscored that the entire ZLZ staff would be retained, including two daughter companies in line with an agreement with the Croatian government guaranteeing current working conditions for a period of at least five years.
Transport Minister Sinisa Hajdas Doncic said that the airport investment was valued at EUR 236 million and the end result would be to increase the number of passengers coming to Zagreb and that the airport would become one of the regional junctures for air traffic.
(Hina)