Minister Butković visited construction sites of the Omiš tunnel and Omiš port

Transport and Infrastructure Minister Oleg Butković visited construction sites in Omiš on Thursday including the Omiš bypass and connection to Cetina Bridge as well as works to the town's port, announcing that the bypass Omiš-Split road should be completed by the end of 2025.
 
Butković underscored that the Omiš bypass is one of the biggest infrastructure projects in Split-Dalmatia County and is valued at HRK 180 million.
 
The  access road to the bridge should be completed by the end of this year and next spring a section of 3.5 kilometres should be completed, he added.
 
A multimodal platform that is on that section is being financed from the next EU perspective. Butković announced that a call for tenders would be advertised by the end of this year for the road to Dugi Rat.
 
The Omiš bypass included two tunnels and a bridge across the Cetina River, the minister explained and added that the Komorjak tunnel is more than 600 metres long and the Omiš tunnel is just over 500 metres while the bridge is 216 metres long.
 
(Hina)

Announcements